SCHEDULING ANALYSIS IN CONSTRUCTION WITH THE PERT METHOD USING MICROSOFT PROJECT
DOI:
https://doi.org/10.56127/ijst.v2i3.1099Abstract
Since 2017, the Drinking Water Supply System (SPAM) of the Capital District (IKK) Ibu has not been functioning due to damage to the pipe network due to road widening work, damage to generators and pumps, thus PDAM West Halmahera will build a new SPAM network system with a gravity system and will analyze scheduling using the Program Evaluation and Review Technique (PERT) method using Microsoft Project 2021 to carry out development planning which has results where the time required for construction is 320 days and can be completed with a percentage level of 95.35%, with a critical path found in the implementation work occupational health and safety, preparation, piping work, procurement and installation of house connections and commissioning test work with a time of 273 days.
References
Romli Stefry. (2022). Pemodelan Risiko Terhadap Pelaku Pekerjaan KonstruksiSistem Penyediaan Air Minum (SPAM) Di Kabupaten Minahasa Selatan. 12(1), 1–14.
Yudha Andika Pratama. (2020). Analisis Penjadwalan Proyek Dengan Metode PERT. Universitas Islam Indonesia.
Sri Kiswati dan Ummi Chasanah. (2019). Analisis Konsultan Manajemen Konstruksi Terhadap Penerapan Manajemen Waktu Pada Pembangunan Rumah Sakit Di Jawa Tengah. Neo Teknika, 5(1), 1–7.
Danang Isnubroto, (2021). Analisis Penjadwalan Dan Alokasi Sumber Daya Pada Proyek Konstruksi Menggunakan Microsoft Project (Studi Kasus Pekerjaan Struktur Proyek XYZ). Wahana Teknik Sipil. 26(6), 1-14.
Achamd Siddiq, (2022). Analisis Penjadwalan Menggunakan Aplikasi Microsoft Project 2010 (Studi Kaus: Ruang Terbuka Hijau Kabupaten Wajo). 2(1), 1-12
Teranau, T. (2023). Analisis Penjadwalan Pekerjaan Saluran Drainase Jalan Lintas Selatan Lot.6 Kabupaten Tulungagung Dengan Metode PERT. Ilmiah Teknik Dan Manajemen Industri, 3(1), 1–14.
Wiji Yuwono. (2021). Kajian Metode PERT-CPM dan Pemanfaatannya dalam Manajemen Waktu dan Biaya Pelaksanaan Proyek. JEMATech, 4(2), 1–23.
Abdurrasyid. (2019). Implementasi Metode PERT dan CPM pada Sitem Informasi Manajemen Proyek Pembangunan Kapal. Ilmu Komputer Dan Informatika, 5(1), 1–9.
Wahyudin Febriana. (2021). Analisis Penjadwalan Proyek Dengan Metode PERT Menggunakan Microsoft Project 2016. Jurnal Ilmu Teknik Sipil Surya Beton. 5(3), 1-9.
Soeharto, I.1995. Manajemen Proyek dari Konseptual sampai Operasional. Erlangga: Jakarat.