EVALUATION OF TIME AND COST PERFORMANCE ON THE GX OFFICE & CO WORKING BALI PROJECT USING THE EARNED VALUE METHOD
DOI:
https://doi.org/10.56127/ijst.v3i2.1337Keywords:
Earned Value Method, Project Delay, Schedule Performance Index, Cost Performance IndexAbstract
In rapid construction developments, delays still occur frequently and have not been resolved, as experienced by the GX Office & Co Working Bali project. The project will be completed in 42 weeks, but in the 27th week, there is an indication of a delay of -4.31% from the initial plan. Earned Value Method (EVM) is a time and cost performance assessment method that can be used to develop strategies to minimize delays. This research aims to evaluate the time and cost performance of the GX Office & Co Working Bali project using the EVM method. A quantitative approach is used to collect and analyze project schedules, actual costs, and progress reports. EVM key indicators such as Planned Value (PV), Earned Value (EV), and Actual Cost (AC) are analyzed to determine Schedule Variance (SV), Cost Variance (CV), Schedule Performance Index (SPI), and Cost Performance Index (CPI). The results showed that the project experienced delays, especially from week 1 to week 14 and week 19 to week 27, with SPI values mostly below 1. However, the project showed increased efficiency in cost management with values CPI above one after week 14 to week 27, indicating that the actual costs incurred are lower than the value of the work completed. These findings highlight the need for corrective actions and more effective management strategies to address delays efficiently in terms of costs.
References
H. Nainggolan et al., Green Technology Innovation: Transformasi Teknologi Ramah Lingkungan berbagai Sektor. PT. Sonpedia Publishing Indonesia, 2023.
J. Thoengsal, Konsep Konstruksi Hijau (Green Construction). Insight Mediatama, 2024.
A. J. Yuwono and B. Setiawan, “Analisis Faktor Keterlambatan Proyek Konstruksi Manara 17 PWNU Jatim,” in Prosiding Seminar Nasional Teknik Sipil UMS, 2023, pp. 604–609.
J. Andrean L, “Faktor–Faktor Penyebab Keterlambatan Proyek Konstruksi Di Yogyakarta.” Universitas Atma Jaya Yogyakarta, 2020.
P. T. S. Balido, H. T. Tjendani, and B. Witjaksana, “Analysis Of Implementation Delays Using The Earned Value Method ( On The Purwosari - Sekarmojo Road Works , Pasuruan District ),” Int. J. Adv. Technol. Eng. Inf. Syst., vol. 3, no. 1, pp. 105–118, 2024.
I. Y. Pramadha, H. T. Tjendani, and B. Witjaksana, “Cost And Time Analysis Using Earned Value Method On The Construction Of The National Kediri Airport Access Road Phase 1 Kediri - Nganjuk,” Int. J. Adv. Technol. Eng. Inf. Syst., vol. 3, no. 1, pp. 119–130, 2024.
L. I. Zhanli, “A brief analysis of the defects and countermeasures of EVM in project management,” in Journal of Physics: Conference Series, 2020, vol. 1648, no. 4, p. 42095.
R. Hasan, S. A. Chowdhury, and J. Akter, “Construction project monitoring: The cost and schedule control by Earned Value Method (EVM),” J. Technol. Manag. Bus., vol. 8, no. 1, pp. 1–9, 2021.
M. Proaño-Narváez, C. Flores-Vázquez, P. Vásquez Quiroz, and M. Avila-Calle, “Earned value method (EVM) for construction projects: Current application and future projections,” Buildings, vol. 12, no. 3, p. 301, 2022.
M. Priyo and T. Zhafira, “Penerapan Metode ‘Earn Value’ Dan ‘Project Crashing’ Pada Proyek Konstruksi: Studi KasusPembangunan Gedung IGD RSUD Sunan Kalijaga, Demak,” Semesta Tek., vol. 20, no. 1, pp. 29–50, 2017.
A. Jatnika and G. J. Johari, “Analisis Pengendalian Waktu dengan Earned Value Concept Pembangunan Rumah Susun Jawa Barat 2 TA. 2019 Universitas Garut,” J. Konstr., vol. 19, no. 1, pp. 336–346, 2021.
A. C. Borges and M. F. Asa, “Analisis Pengendalian Biaya Dan Waktu Menggunakan Metode Nilai Hasil (Earned Value) Pada Kasus Pembangunan Gedung Puskesmas Lumbang Di Kabupaten Probolinggo,” J. Sustain. Infrastruct., vol. 2, no. 1, 2023.
F. Setiawan and M. Ihsan, “Pengendalian Waktu Pelaksanaan Project Dengan Menggunakan Earned Value Concept,” J. Tek. SIPIL CENDEKIA, vol. 4, no. 1, pp. 472–518, 2023.
S. Janizar, “Penerapan Metode Earned Value Analysis Terhadap Waktu Penjadwalan,” J. Konstr., vol. 21, no. 1, pp. 113–120, 2023, doi: 10.33364/konstruksi/v.21-1.1328.
C. N. Lumentah, T. T. Arsjad, and G. Y. Malingkas, “Pengendalian biaya dan waktu pada proyek pembangunan ruko di area Perumahan Kharisma Koka Minahasa menggunakan metode konsep nilai hasil,” J. Sipil Statik, vol. 8, no. 1, 2020.
S. Trafolta and A. Fernando, “Penerapan Metode Earned Value Pada Tinjauan Proyek Pembangunan Gedung Sekolah Tinggi Agama Katolik Negeri (STAKatN),” J. Retensi, vol. 2, no. 2, pp. 1–8, 2022.
M. Vanhoucke and M. Vanhoucke, “Earned value management,” Integr. Proj. Manag. Sourceb. A Tech. Guid. to Proj. Sched. Risk Control, pp. 199–250, 2016.
R. S. Mathpati and A. S. Wayal, “Continuous Project Evaluation of An Infrastructure Using Earned Value Analysis.” Volume.
F. Susilowati and W. M. Kurniaji, “Effective performance evaluation to estimate cost and time using earned value,” in IOP conference series: Materials science and engineering, 2020, vol. 771, no. 1, p. 12055.