Working Method of Column Casting In Residential House Construction Project at Jl. Martimbang No.2

Authors

  • Rifaldi Adi Saputra Universitas Dian Nusantara
  • Agung Sakti Meldian Universitas Dian Nusantara
  • Lutfi Hanafi Universitas Dian Nusantara
  • Aep Saepuloh Univeristas Nusa Megar Kencana

DOI:

https://doi.org/10.56127/jts.v4i2.2227

Keywords:

Column, Implementation Method, Column Structure. Quality control

Abstract

Column work is one of the important stages in constructing a residential house structure, functioning as the main element supporting the load. In the house construction project at Jalan Martimbang No. 2, South Jakarta, the column implementation method is designed to prioritize the accuracy, strength, and durability of the structure. The stages of work include material preparation, formwork manufacture, assembly and installation of reinforcement, and concrete casting according to the established technical specifications. The entire process is carried out by paying attention to quality standards and work safety procedures, as well as considering the conditions of the surrounding environment. With a systematic approach and the use of quality materials, it is expected that the column structures will be able to support the building optimally and meet the planned lifespan of the building.

References

Strong Lukiyanto . Mandor, Leadership Model Traditional Javanese On Project Modern Era Construction . Edited by Maranatha Wijayaningtiyas . Jakarta, 2016.

Muhammad Ridwan Prayoga , Adhi Purnomo, et al . “ Analysis and Optimization Casting Time Management Concrete Structure On Project Construction : A Case Study of Delays Casting of Columns, Beams, and Plates.” Tambusai Education 8 (2024): 350–58.

Prayoga , Muhammad Ridwan, Adhi Pmomo , and Arief Saefudin . “ Analysis and Optimization Casting Time Management Concrete Structure On Project Construction : A Case Study of Delays Casting of Columns, Beams, and Plates.” Tambusai Education Journal 8 (2024): 350–58.

Rantung, Audy HP, Bonny F Sompie , and Robert JM Mandagi . “ Analysis Control Costs And Schedules At Stage Implementation Construction With ' Earned Value Analysis'. ” Journal Scientific Media Engineering, Civil Engineering Sam Ratulangi University Manado 4, no. 3 (2014): 190–203. http://ejournal.unsrat.ac.id/index.php/jime/article/view/6396/5912.

Arais Sastra (2019) Implementation Method Column Work and Calculation of Concrete Volume of Semi Basement Floor Columns As 31B ( Gunadarma University ).

Deva Agung Putra Pratama (2022) Review of Implementation Methods Work Structure of Beams, Columns and Floor Plates in the Traditional Village Council (MDA) Building, Klungkung Regency ( Bali State Polytechnic ).

Mohammad Khoirun Nasikhin , Arik Triarso (2023) Implementation Method Work Column Structure in the Passenger Terminal Building Construction Project of Dhoho Kediri International Airport (State University of Surabaya).

Nida Nahdia Vilanti (2018) Implementation Method Column Work Using Formwork Sateco and Productivity Analysis Formwork Sateco on the Patra Jasa Cirebon (UGM) Hotel Project .

Navy, Edward G, 1990, Reinforced Concrete A Basic Approach , PT. Eresco , Bandung. Pamungkas , AFS, & Yasin, N. (2020). Implementation Method , Column Work and Calculation

Casting Volume On Mandiri Tower Project Wijayakusma .

Calculation Procedures Concrete Structure For Building Construction .

Sudarmoko , 1996. Reinforced Concrete Column Design Diagram , Civil Engineering Department , Faculty of Engineering, Gadjah Mada University, Yogyakarta

Downloads

Published

2025-08-30

How to Cite

Rifaldi Adi Saputra, Agung Sakti Meldian, Lutfi Hanafi, & Aep Saepuloh. (2025). Working Method of Column Casting In Residential House Construction Project at Jl. Martimbang No.2. Jurnal Teknik Dan Science, 4(2), 117–125. https://doi.org/10.56127/jts.v4i2.2227

Similar Articles

1 2 3 4 5 6 7 > >> 

You may also start an advanced similarity search for this article.