Analysis of the Accelerated Implementation of the North Boulevard Paramount Petals Road and Canal Project Using CPM, PERT And Time Cost Trade Off Integration Methods
DOI:
https://doi.org/10.56127/jts.v4i3.2301Keywords:
Development Project, Critical Path Method, Program Evaluation and Review Technique, Time Cost Trade OffAbstract
The North Boulevard Road and Canal Project in the South Petals area is a project that has been under construction since June 2024 and is the main route for the Paramount Petals neighborhood. This project has a work time agreement of 120 normal days. For this reason, it is very important for the project to be completed on time or faster and not experience delays. In this final project, an analysis of project acceleration is carried out using the Critical Path Method scheduling method to determine the activities that are on the critical path and the Program Evaluation and Review Technique to determine the probability that the project can be completed on time. Based on the analysis carried out, it was found that the CPM duration is 120 days with the probability that it can be completed in 120 days is 50.38%. Then the results of the acceleration analysis using the Time Cost Trade Off method show that the optimal project duration is 100 working days with a normal reduction of Rp. 76,604,480.00 in addition to 1 hour of overtime work.
References
Astari, N. M., Subagyo, A. M., & Kusnadi. (2021). Project Management Planning Using CPM (Critical Path Method) and PERT (Program Evaluation And Review Technique) Methods. 13(1), 164–180. https://journal.umsurabaya.ac.id/Agregat/article/view/9154
Bashuru M. and Douglas K. B (2022). Optimal Project Management Schedule for PhD Studies with Focus on Selected Northern Sector Universities in Ghana Using CPM and PERT: American Journal of Operations Research: 12(1): 1-6
Indonesia Number KEP.102/MEN/VI/2004 Overtime Working Time and Overtime Wages, Jakarta: Department of Public Works.
Maduagu. E. N. (2022. Critical path method (cpm) network as a tool for effective project execution in some selected construction firms in Enugu state. Marketing and Management Sciences: European Journal of management Sciences Volume:5;Issue:02, ISSN:2263-6684 Impact Factor: 3.426
R. Rosalinda, N. Nizmah, R. Suko Ari, M. Makmur, and D. Rarasanti, "Analysis of Project Time and Cost Control with CPM, PERT and Crashing Project Methods in Shop Building Projects at cv. Mentari Permai," Scientific Journal of Reflection: Economic, Accounting, Management, & Business, vol. 6, no. 1, pp. 85–94, Jan. 2023, https://doi.org/10.37481/sjr.v6i1.622.
Setiawan, Bagus Budi, 2012, Time and Cost Trade-Off Analysis Using the Time Cost Trade Off (TCTO) Method on Building Construction Projects in Jakarta, Construction Journal Vol.4, No.1, Page. 27, Jakarta: Muhammadiyah University Jakarta.
Saputra, N., Handayani, E., & Dwiretnani, A. (2021). Project Scheduling Analysis using the Critical Path Method (CPM) Case Study of the Construction of an Inpatient Building at Abdul Manap Hospital, Jambi City. Civil Talent Journal, 4(1), 44–52. https://doi.org/10.33087/talentasipil.v4i1.48