TIME ANALYSIS USING EARNED VALUE METHOD ON PRESERVATION OF SECTION 5 PANDAAN TOLL EXIT ROAD IN MALANG

Authors

  • Amalia Fathimah Azh Zhahra Mughni 17 Agustus 1945 Surabaya University
  • Hanie Teki Tjendani 17 Agustus 1945 Surabaya University
  • Budi Witjaksana 17 Agustus 1945 Surabaya University

DOI:

https://doi.org/10.56127/ijst.v3i1.1228

Keywords:

Earned Value Method, Time Performance Analysis, Cost Performance Analysis, Project Control, Actual Cost Estimation.

Abstract

The development of a country's road or toll road infrastructure  can be used as a benchmark to judge a country's economic development at both macro and micro levels. The location of toll exits has a significant impact on labor absorption and the creation of new business activities.

Projects are dynamic, so contractors must adapt to changing project situations and conditions  if they are to succeed in achieving optimal profits. Today's highly competitive aspects of construction planning require high levels of accuracy,  efficiency, effectiveness and economy in project analysis. In the world of construction projects, there is much that can be done, including controlling costs.  In cost control, efforts can be made so that the realization of costs incurred is consistent with implementation needs  and is not excessive, such as efforts to limit costs, that is, to realize savings without does not reduce quantity or quality. The earned value method is used to determine the project's performance in terms of cost at a certain time, determine the project's performance in terms of progress/time at a point in time. certain, estimate the cost to complete the project after the evaluation period and estimate the cost to complete the project after the evaluation period. Project completion time after evaluation. In this study, the author performed a cost analysis using the earned value method for the conservation of Pandaan Malang Section 5 toll road. The schedule variance value is Rp1,652,192,521 with the time performance index value of 1.139743112 or SPI value > 1, meaning this project has arrived at week 17, the implementation is faster than planned.The estimated project completion date or Expected Schedule (EAS) is 278 days,  22 days faster than the total contract period of 300 days.

References

AACE® International Recommended Practice. (n.d.). Cost Engineering Terminology. Retrieved November 15, 2023, from https://library.aacei.org/terminology/welcome.shtml

Abd. Rahman Rasidin, Muh. Nashir T., & Hendro Widarto. (2022). Studi Kelayakan Pembangunan Jalan Lingkar Tengah Kota Parepare. Jurnal Karajata Engineering, 2(1), 19–25.

https://doi.org/10.31850/karajata.v2i1.1632

Akbar, R. W., & Maliki, I. (2018). Pembangunan Sistem Informasi Manajemen Sumber Daya Manusia Di Pt. Saekan Bumi Persada. 1–10. https://elibrary.unikom.ac.id/id/eprint/414/

Alfadin, M. R., & Witjaksana, B. (2023). Analisis Biaya dan Waktu dengan Metode Nilai Hasil (Studi Kasus : Preservasi Jembatan Sembayat Di Gresik). Ensiklopedia Of Journal, 5(4).

https://doi.org/https://doi.org/10.33559/eoj.v5i4.1741

Arifin, Z. (2017). Modul 01 Pengantar Manajemen Proyek (Vol. 01).

https://pustaka.ut.ac.id/lib/wp-content/uploads/pdfmk/MSIM4406-M1.pdf

Arsjad, T. T., & Malingkas, Y. G. (2020). Pengendalian Biaya Dan Waktu Pada Proyek Pembangunan Ruko Di Area Perumahan Kharisma Koka Minahasa Menggunakan Metode Konsep Nilai Hasil. Jurnal Sipil Statik, 8(1), 53–64.

Balai Besar Pelaksanaan Jalan Nasional (BBPJN) Jawa Timur. (2022). Dokumen Suplemen Dokumen Evaluasi Lingkungan Hidup ( DELH ) Pembangunan / Peningkatan Jalan Jawa Timur – 2 Exit Toll Seksi 5 Pandaan – Malang (Issue November).

https://p3tb.com/uploads_file/20230216.3661.Supplement_DELH_Preservasi_Jalan_pada_Exit_Tol_Pandaan_Malang_P3TB.pdf

Fauzy, Y., Mochtar, B., & Marzuki, R. (2020). Analisa Biaya Dan Waktu Dengan Metode ( Earned Value Analysis ) Pada Lanjutan Peningkatan Jalan Awang Long – Jalan Darmawan Desa Kota Bangun Ilir Kecamatan Kota Bangun. Kurva S Jurnal Keilmuan Dan Aplikasi Teknik Sipil, 11(1), 1–13. http://ejurnal.untag-smd.ac.id/index.php/TEK/article/view/5238/4984

Fleming, Q. W., & Koppelman, J. M. (1994). The Essence of Evolution of Earned Value.

Peraturan Gubernur Jawa Timur Nomor 33 Tahun 2022 Tentang Harga Satuan Pokok Kegiatan Pemerintah Provinsi Jawa Timur, 1 (2023).

https://peraturan.bpk.go.id/Download/222949/2022PERGUBJATIM033.pdf

Peraturan Gubernur Jawa Timur Tentang Standar Satuan Harga Barang Pemerintah Provinsi Jatim Tahun 2022, Pub. L. No. 30/2022, 31 (2023).

https://peraturan.bpk.go.id/Download/222888/2022PERGUBJATIM030.pdf

Hansen, S. (2015). Manajemen Kontrak Konstruksi (1st ed.). PT. Gramedia Pustaka Utama. https://scholar.google.co.id/scholar?oi=bibs&cluster=16577217016900568223&btnI=1&hl=en

Harefa, M. B., & Surbakti, A. A. (2021). Pengendalian Pelaksanaan Pada Proyek Jalan Dengan Earned Value Analysis. Juitech, 5(2), 14–22.

http://www.portaluniversitasquality.ac.id:5388/Ojssystem/index.php/JUITECH/article/download/627/pdf

Herman, F., & Saleh, S. M. (2011). Biaya Preservasi Jalan Akibat Truk Dengan Beban Berlebih di Jalan Pesisir Timur Provinsi Aceh. Jurnal Transportasi, 11(3), 219–228.

https://journal.unpar.ac.id/index.php/journaltransportasi/article/view/460/444

Maulidi, N., Huda, M., & Tjendani, H. T. (2021). Analisis Biaya dan Waktu Pada Pembangunan Gedung Trauma Center Dan Intensive Care Tahap IV RSUD Dr. Soedono Madiun dengan Metode Earned Value. Jurnal Spesialis Teknik Sipil, 2(2).

https://jurnal.untag-sby.ac.id/index.php/JSpTS/article/view/7088/5004

Pedoman Penyusunan Perkiraan Biaya Pekerjaan Konstruksi Bidang Pekerjaan Umum dan Perumahan Rakyat Tahun 2022, Pub. L. No. 01/2022, Kementrian PUPR 1 (2022).

https://jdih.pu.go.id/internal/assets/assets/produk/PermenPUPR/2022/01/PermenPUPR1.zip

Nastiti, H., Suryana, D. S., Aulia, F. R. F., & Ramsyahdira, M. R. (2023). Control Analysis of the Griya Jenggala Development Project using the Earned Value Method at PT Sarana Loka Almika in Kebayoran. Journal of Innovation and Community Engagement, 4(3), 174–191.

https://doi.org/10.28932/ice.v4i3.7346

Nufah, Y. W., Yanti, G., & Lubis, F. (2019). Analisis Proyek Dengan Metode Earned Value Concept (Studi Kasus Pada Proyek Pembangunan Jalan Tol Ruas Pekanbaru – Dumai Seksi 2 Sta. 9+500 – 33+600). Prosiding Seminar Nasional Cendekiawan, 5, 1.59.1-1.59.7.

https://trijurnal.lemlit.trisakti.ac.id/index.php/semnas/article/view/5740

Peraturan Walikota Malang nomor 10, Pub. L. No. 10/2022, Harga Satuan Pekerjaan Konstruksi 1 (2022). https://peraturan.bpk.go.id/Download/221352/Salinan Perwal No 10 Tahun 2022 Ttg Harga Satuan Pekerjaan Konstruksi.pdf

Peraturan Menteri Pekerjaan Umum Republik Indonesia Nomor 13/PRT/M/2011 Tentang Tata Cara Pemeliharaan Dan Penilikan Jalan, Menteri Pekerjaan Umum Republik Indonesia 1 (2011).

https://peraturan.bpk.go.id/Download/136608/PermenPU13-2011.pdf

PPK 3.6 SATKER PJN WIL III PROVINSI JAWA TIMUR BBPJN JATIM BALI. (2023). Uraian Singkat Preservasi Jalan Pada Exit Tol Seksi 5 Pandaan Malang. 3–5.

https://lpse.pu.go.id/eproc4/dl/b070fae498f37e56181275810d2b0d2b360631800f75dfeace99b3f9729040e323518417a8f8bc12284b9507a8e0133c957265cb391927718ca34459e5ee45b3f4552532dde04724189ccb8bc67ec0304ceea7a78e683f47b2cff8ca7d4e557569da8d910c60f0201d7d48c2027d066

Pratama, F., Waluyo, R., & Puspasari, V. H. (2019). Analisis Kinerja Proyek Peningkatan Jalan Pelantaran-Parenggean-Tumbang Sangai Dengan Metode Earned Value. Oktober, 3(1), 1–10.

https://e-journal.upr.ac.id/index.php/JT/article/view/1325/1109

Proaño-Narváez, M., Flores-Vázquez, C., Vásquez Quiroz, P., & Avila-Calle, M. (2022). Earned Value Method (EVM) for Construction Projects: Current Application and Future Projections. Buildings, 12(3), 301. https://doi.org/10.3390/buildings12030301

Project Management Institute. (2017). A Guide to The Project Management Body of Knowledge. In Inc. The Project Management Institute (Ed.), Project Management Institute, Inc. (6th ed., Vol. 2, Issue 1). Project Management Institute.

Ridha, R., Syarwan, & Supardin. (2020). Analisis Waktu dan Biaya Proyek Peningkatan Jalan Tgk. Muda Lamukta Lhokseumawe dengan Metode Earned Value. Jurnal Sipil Sains Terapan, 03(2), 1–75.

https://e-jurnal.pnl.ac.id/JSST/article/view/3105/2565

Ritz, G. J. (1994). Total Construction Project Management (Vol. 2013).

Surat Edaran Nomor 09/SE/Db/2021 tentang Perencanaan dan Pemrograman Pekerjaan Preservasi Jaringan Jalan (Bagian Dari Manajemen Aset Prasarana Jalan), Surat Edaran Dirjen Bina Marga 2021 1 (2021).

https://binamarga.pu.go.id/index.php/peraturan/dokumen/surat-edaran-nomor-09sedb2021-tentang-perencanaan-dan-pemrograman-pekerjaan-preservasi-jaringan-jalan-bagian-dari-manajemen-aset-prasarana-jalan

Sidiq, A. P., & Johari, G. J. (2022). Analisis Penerapan Earned Value Terhadap Manajemen Waktu dan Biaya pada Proyek Jembatan Cibuni. Jurnal Konstruksi, 20(1), 139–150.

https://doi.org/10.33364/konstruksi/v.20-1.1036

Soeharto, I. (1999). Manajemen Proyek (Dari Konseptual Sampai Operasional). In Penerbit Erlangga (2nd ed., Vol. 1). Penerbit Erlangga.

Soemardi, B. W., Wirahadikusumah, R. D., Abduh, M., & Pujoartanto, N. (2006). Konsep Earned Value untuk Pengelolaan Proyek Konstruksi. Institut Teknologi Bandung, 1–13.

https://www.academia.edu/2979947/Konsep_Earned_Value_untuk_Pengelolaan_Proyek_Konstruksi

Sugiyanto, S., & Kosbiamtoro, A. (2022). Analisis Kinerja Biaya Pada Proyek Rehabilitasi Drainase Dan Trotoar Jalan Teuku Umar Paket I Dengan Metode Earned Value. Jurnal Litbang Sukowati : Media Penelitian Dan Pengembangan, 5(2), 126–141. https://doi.org/10.32630/sukowati.v5i2.320

Susanti, B., Melisah, M., & Juliantina, I. (2019). Penerapan Konsep Earned Value Pada Proyek Konstruksi Jalan Tol (Studi Kasus Ruas Jalan Tol Kayuagung - Palembang -Betung). Jurnal Rekayasa Sipil (JRS-Unand), 15(1), 12. https://doi.org/10.25077/jrs.15.1.12-20.2019

Tangtobing, R. F. F., & Waty, M. (2023). Penerapan Metode Earned Value Dan Earned Schedule Pelaksanaan Proyek Rumah Sakit X Di Bandung. JMTS: Jurnal Mitra Teknik Sipil, 6(2), 237–248. https://doi.org/10.24912/jmts.v6i2.22251

Tenggara, M. A. P., Agustin, I. W., & Hariyani, S. (2021). Kinerja Jalan Di Kota Surabaya Berdasarkan Tingkat Pelayanan Jalan. Planning for Urban Region and Environment, 10(3), 119–128. https://purejournal.ub.ac.id/index.php/pure/article/view/194/149

Widiasanti, I., & Lenggogeni. (2013). Manajemen Konstruksi. In P. Latifah (Ed.), Remaja Rosdakarya. PT Remaja Rosdakarya.

Zakariyya, B., Ridwan, A., & Suwarno, S. (2020). Analisis Biaya Dan Jadwal Proyek Pembangunan Gedung Dinas Kesehatan Kabupaten Trenggalek Dengan Metode Earned Value. Jurnal Manajemen Teknologi & Teknik Sipil, 3(2), 362. https://doi.org/10.30737/jurmateks.v3i2.1197

Zanuardi, A., & Suprayitno, H. (2018). Analisa Karakteristik Kecelakaan Lalu Lintas di Jalan Ahmad Yani Surabaya melalui Pendekatan Knowledge Discovery in Database. Jurnal Manejemen Aset Infrastruktur & Fasilitas, 2(1), 45–55. https://doi.org/10.12962/j26151847.v2i1.3767

Downloads

Published

2024-03-31

How to Cite

Amalia Fathimah Azh Zhahra Mughni, Hanie Teki Tjendani, & Budi Witjaksana. (2024). TIME ANALYSIS USING EARNED VALUE METHOD ON PRESERVATION OF SECTION 5 PANDAAN TOLL EXIT ROAD IN MALANG. International Journal Science and Technology, 3(1), 36–50. https://doi.org/10.56127/ijst.v3i1.1228

Similar Articles

1 2 3 4 5 6 7 > >> 

You may also start an advanced similarity search for this article.

Most read articles by the same author(s)

Obs.: This plugin requires at least one statistics/report plugin to be enabled. If your statistics plugins provide more than one metric then please also select a main metric on the admin's site settings page and/or on the journal manager's settings pages.