Time and Cost Performance Evaluation Using Earned Value Management in Residential Construction Projects

A Case Study of the Hanglekir Housing Development

Authors

  • Riris Setiyowati Universitas Dian Nusantara, Indonesia
  • Jalaludin Jalaludin Universitas Dian Nusantara, Indonesia

DOI:

https://doi.org/10.56127/juit.v5i1.1411

Keywords:

Earned Value Management, construction project performance, schedule performance index, cost performance index, construction project management

Abstract

Construction projects frequently experience discrepancies between planned schedules and actual implementation, resulting in delays and cost inefficiencies. Therefore, effective monitoring is needed to evaluate project performance and maintain alignment with planned time and budget targets. Objective: This study evaluates the time and cost performance of the Hanglekir Residential Housing Development Project using the Earned Value Management (EVM) approach. Methodology: This research employed a mixed-method case study design. Quantitative data were obtained from project documents, including cost budget plans, schedules, and progress reports, while qualitative data were collected through field observations and interviews. Project performance was analyzed using EVM indicators, namely Schedule Variance (SV), Cost Variance (CV), Schedule Performance Index (SPI), Cost Performance Index (CPI), and forecasting indicators such as Estimate at Completion (EAC) and Estimate at Schedule (EAS). Findings: The results indicate that the project experienced schedule delays, as shown by SPI values consistently below 1. However, cost performance was relatively efficient in several periods, reflected by CPI values above 1. Forecasting results show that the final project cost is likely to remain below the initial budget, while the completion time is expected to slightly exceed the planned schedule. Implications: These findings demonstrate the importance of integrated project monitoring to improve time and cost control. Originality: This study provides empirical evidence of the practical application of EVM for evaluating both schedule and cost performance in a residential construction project.

References

BPS, S. I. (2024). Construction Statistics of Indonesia 2024. https://www.bps.go.id

Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. (2012). Analysing Factors Affecting Delays in Indian Construction Projects. International Journal of Project Management, 30(4), 479-489. https://doi.org/10.1016/j.ijproman.2011.10.004

Fleming, Q. W., & Koppelman, J. M. (2016). Earned Value Project Management (4 ed.). Project Management Institute.

Flyvbjerg, B. (2014). What You Should Know About Megaprojects and Why: An Overview. Project Management Journal, 45(2), 6-19. https://doi.org/10.1002/pmj.21409

Indonesia, C. (2024). Proyek Konstruksi Masih Hadapi Tantangan Kenaikan Harga Material. https://www.cnbcindonesia.com

Khamooshi, H., & Golafshani, H. (2014). EDM: Earned Duration Management, a New Approach to Schedule Performance Management and Measurement. International Journal of Project Management, 32(6), 1019-1041. https://doi.org/10.1016/j.ijproman.2013.11.002

Kim, B. C., & Reinschmidt, K. F. (2010). Probabilistic Forecasting of Project Duration Using Kalman Filter and Earned Value Method. Journal of Construction Engineering and Management, 136(8), 834-843. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000192

Kompas.com. (2023). Kenaikan Harga Material Bangunan Picu Keterlambatan Proyek Konstruksi. https://www.kompas.com

Lipke, W. (2003). Schedule Is Different. The Measurable News(3), 31-34.

Love, P. E. D., Edwards, D. J., & Irani, Z. (2012). Moving Beyond Optimism Bias and Strategic Misrepresentation: An Explanation for Social Infrastructure Project Cost Overruns. IEEE Transactions on Engineering Management, 59(4), 560-571. https://doi.org/10.1109/TEM.2011.2163628

Vanhoucke, M. (2012). Measuring the Efficiency of Project Control Using Fictitious and Empirical Project Data. International Journal of Project Management, 30(2), 252-263. https://doi.org/10.1016/j.ijproman.2011.05.006

Downloads

Published

2026-02-28

How to Cite

Setiyowati, R., & Jalaludin, J. (2026). Time and Cost Performance Evaluation Using Earned Value Management in Residential Construction Projects: A Case Study of the Hanglekir Housing Development. Jurnal Ilmiah Teknik, 5(1), 306–324. https://doi.org/10.56127/juit.v5i1.1411