Analysis of Delay Factors in the Capital Expenditure Package and Public Facilities Project of Turyapada Tower Technology Park KBS 6.0 Kerthi Bali
DOI:
https://doi.org/10.56127/juit.v4i3.2287Keywords:
Project delay, causative factors, Turyapada Tower Technology Park, construction management, quantitative analysisAbstract
Delays in construction projects often impact cost, time, and quality. This study was conducted on the Turyapada Tower Technology Park KBS 6.0 Kerthi Bali project, which experienced delays from its initial schedule. The aim of the research is to identify and analyze the dominant factors contributing to project delays. Using a quantitative method through questionnaires distributed to 50 respondents and data analysis with validity tests, reliability tests, and Pearson correlation in SPSS, the results indicate that environmental and equipment factors are the primary causes of delays, followed by labor, management, execution methods, and materials. The dominant factors show a very strong correlation with project schedule delays. These findings are expected to serve as an evaluation and input to improve timeliness and efficiency in similar projects in the future.
References
Desiana, I. (2020). Factors causing delays in the implementation of construction project work. Civil Engineering Journal, 9(2), 88–95. https://e-jurnal.pnl.ac.id/portal/article/view/5302
Gunawan, R., Wahyuni, T., & Pohan, M. (2025). Analysis of the causes of delays in water resources construction projects in Riau Islands Province. Jurnal Teknik Sipil ITP, 22(1), 51–62. https://jts.itp.ac.id/index.php/jts/article/view/920
Hassan, H., Mangare, J. B., & Pratasis, P. A. K. (2016). Factors causing delays in construction projects and alternative solutions (Case study: Manado Town Square III). Jurnal Sipil Statik, 4(11), 657–664.
Johari, M., & Gunawan, F. (2024). Evaluation of infrastructure project delays in Garut Regency. Indonesian Construction Journal, 8(1), 34–42. https://jurnal.itg.ac.id/index.php/konstruksi/article/view/887
Kerzner, H. (2017). Project management: A systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Megawati, D., & Lirawati, F. (2024). Building project delays due to weak field management. Journal of Civil Engineering, Pakuan University, 5(2), 76–84. https://journal.unpak.ac.id/index.php/jurnalteknik/article/view/3282
Melly, S., Haryono, I., Mulyati, E., & Setyawati, D. (2023). Project management (E. J. Atmaja, Ed.). HEI Publishing Indonesia.
Munns, A. K., & Bjeirmi, B. F. (1996). The role of project management in achieving project success. International Journal of Project Management, 14(2), 81–87.
Ni Made Sintya Rani, & Ni Kadek Sri Ebtha Yuni. (2021). Risk factor analysis of construction project delays at The Himana Condotel. PADURAKSA: Journal of Civil Engineering, Warmadewa University, 10(1), 41–55. https://doi.org/10.22225/pd.10.1.2367.41-55
Rahmadani, S., Wulandari, M., & Ismail, A. (2023). Evaluation of implementation methods on delays in laboratory building projects. Journal of System Optimization, 7(1), 12–20. https://jurnal.polinema.ac.id/index.php/jos-mrk/article/view/3853
Rauzana, A., Gunawan, & Masimin. (2016). Analysis of inhibiting factors affecting irrigation project schedules in Aceh Province. Civil Engineering Journal, Syiah Kuala University, 5(3).
Rizal, A. H., Agon, Y. U., & Bella, R. A. (2023). Factors inhibiting performance time in building construction projects. Civil Engineering Journal, 12(1).
Romadhon, A. F., & Tenriajeng, A. T. (2020). Analysis of factors causing delays in high-rise building projects in Indonesia. Civil Engineering Project Journal, 3(1). https://ejournal2.undip.ac.id/index.php/potensi
Sanaky, M. M., Saleh, L. M., & Titaley, H. D. (2021). Analysis of delay factors in the construction of MAN 1 Tulehu dormitory, Central Maluku. Jurnal Simetrik, 11(1)














