TIME AND COST ANALYSIS OF DHOHO KEDIRI AIRPORT ACCESS ROAD PROJECT USING EARNED VALUE METHOD

Authors

  • Ichsan Yanuansyah Pramadha 17 Agustus 1945 Surabaya University
  • Hanie Teki Tjendani 17 Agustus 1945 Surabaya University
  • Budi Witjaksana 17 Agustus 1945 Surabaya University

DOI:

https://doi.org/10.56127/ijst.v3i1.1229

Keywords:

Time and cost analysis, Earned value method, National Access Roads, Airports

Abstract

Delays in project completion are something that any project contractor must avoid. Because apart from having a negative effect on the credibility of the project contractor, delays in project completion also cause penalty costs to be borne by the contractor, so that the profits to be obtained are reduced.
Earned Value Method. This method is used to determine project performance in terms of costs at one time, determine project performance in terms of schedule/time at one time, predict costs to complete the project after the evaluation time and predict the time to complete the project after the evaluation.
By using this method in the Kediri airport access road construction project, it was found that the project was delayed from the plan. The ETC (estimate to complete) value obtained was the estimated budget value required for completion was IDR 17,470,510,292.77, while the EAC (estimate at complete) value obtained was the final total cost estimate. project is IDR 32,509,153,464.05. TE Value Results (Time Estimate) to complete the project to completion in 89 calendar days or 5 days later than the contract time of 84 calendar days.

References

Suharto, Priest. (1999). Project Management (Volume 1). Airlangga.

Witjaksana, B., & Reresi, S. P. (2012). Project Cost Analysis Using The Earned Value Method In The Performance Process (Case Study Of The Widya Mandala Pakuwon Citi-Surabaya Catholic University Development Project). Untag Surabaya Civil Engineering Journal, 05(02), 45–56

Tjendani, H. T., Anwar, N., & Putu Artama Wiguna, I. (2018). Two Stage Simulation To Optimize Risk Sharing In Performance-Based Contract On National Road A System Dynamic And Game Theory Approach. Arpn Journal Of Engineering And Applied Sciences, 13(15), 4432–4439.

Barry, Render, H.J. (2005). Operations Management (S. Yagan (Ed.); Global Edit). Pearson.

Handoko, T. H. (2000). Basics Of Production And Operations Management (Vol. 1, Issue 1).

Yomelda, & Utomo, C. (2015). Earned Value Analysis Of The Vimala Hills Villa And Resort Bogor Development Project. Its Engineering Journal, 4(1), 76–81.

Civil, J. T., & Civil, F. T. (2015). Muh Izzeul. 4(1). Http://Ejurnal.Its.Ac.Id/Index.Php/Teknik/Article/View/8970

Kusnadi, A. (2015). Earned Value Management (Evm) In Software Project Cost Estimation Using Spiral Development.Ultima Infosys Journal, 6(1), 36–42.

Downloads

Published

2024-03-31

How to Cite

Pramadha, I. Y., Hanie Teki Tjendani, & Budi Witjaksana. (2024). TIME AND COST ANALYSIS OF DHOHO KEDIRI AIRPORT ACCESS ROAD PROJECT USING EARNED VALUE METHOD. International Journal Science and Technology, 3(1), 51–55. https://doi.org/10.56127/ijst.v3i1.1229