Analysis of Design Change Management in a Construction Project at Jl. Duta Permai 2 No. 6, Pondok Indah: Case of Owner Mr. Patrick

Authors

  • Muhammad Malik Abdul Jabbar Dian Nusantara University
  • Era Agita Kabdiyono Dian Nusantara University

DOI:

https://doi.org/10.56127/ijst.v4i2.2289

Keywords:

design changes, project management, cost, quality, time, construction

Abstract

Design changes in construction projects often pose significant challenges, impacting the cost, quality, and timeline of the projects. This study aims to analyze the management of design changes in a construction project located at Jl. Duta Permai 2 No. 6, Pondok Indah, with a focus on identifying the causes, the management strategies implemented, and their overall impact on the project. The research employs a qualitative descriptive method, collecting data through interviews, observations, and analysis of relevant documents. The findings indicate that the primary factors causing design changes include regulatory changes, owner requests, and technical constraints that arise during construction execution. The management strategies applied by the project team, while systematic, still face challenges in communication that can hinder decision-making. The results reveal that poorly managed design changes can lead to project delays and cost increases of up to 20%. This study recommends enhancing communication among stakeholders and providing training on change management to minimize the impacts of design changes in the future. Through this analysis, it is expected to provide insights and references for project managers and future researchers in managing design changes more effectively

References

Adinda, A. (2023). Analisis Perbandingan Biaya Dengan Metode AHSP, BOW, Dan Lapangan (Redesain Islamic Center Lampung Tengah) Doctoral dissertation, Universitas Muhammadiyah Metro).

Alizar, Ir. (2023). Pedoman penulisan tugas akhir/skripsi. Program Studi Teknik Sipil, Fakultas Teknik dan Informatika, Universitas Dian Nusantara.

Badan Standardisasi Nasional. (2014). SNI ISO 21500:2014 – Panduan manajemen proyek. Jakarta: BSN.

Doloi, H. (2012). Cost overruns and failure in project management: Understanding the roles of key stakeholders in construction projects. Journal of Construction Engineering and Management, 138(11), 1367–1378.

Hwang, B. G., & Ng, W. J. (2013). Project management knowledge and skills for green construction: What do project managers need to know? International Journal of Project Management, 31(3), 350–361.

Iwawo, A. M., Dundu, A. K., & Pratasis, P. A. (2024). Analisis Perbandingan Rencana Anggaran Biaya Kontraktor Dengan Perhitungan Biaya Berdasarkan AHSP Permen PUPR No. 1 Tahun 2022 Pada Proyek Pembagunan Rumdis Kodim 1302 Minahasa. TEKNO, 22(88), 1089-1098.

Kementerian Pekerjaan Umum dan Perumahan Rakyat. (2021). Peraturan tentang perubahan desain proyek konstruksi. Jakarta: Kementerian PUPR.

Kerzner, H. (2017). Project management: A systems approach to planning, scheduling, and controlling (12th ed.). Hoboken, NJ: John Wiley & Sons.

Kotter, J. P. (1996). Leading change. Boston, MA: Harvard Business Review Press.

Lewin, K. (1951). Field theory in social science. New York, NY: Harper & Row.

Ode, A. T. La, Syarif, M., Purnama, H., Masdina, Latupeirissa, J. E., Gusty, S., Putri, T. S., Latif, F., Dzakir, L. O., Wiriantari, F., & Pagoray, G. L. (2023). Manajemen Proyek Konstruksi (M. N. La Ola, Ed.). CV. Tohar Media.

Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK® Guide) (7th ed.). Newtown Square, PA: Project Management Institute.

PMI. (2017). A guide to the project management body of knowledge (PMBOK® Guide) (6th ed.). Newtown Square, PA: Project Management Institute.

Rachman, M. (2020). Analisis pengaruh perubahan desain terhadap biaya dan waktu proyek konstruksi: Studi kasus di Jakarta. Jurnal Teknik Sipil, 12(3), 45–60.

Santosa, B., & Pramono, R. (2019). Analisis manajemen risiko pada proyek konstruksi gedung bertingkat di Surabaya. Jurnal Manajemen Konstruksi, 7(2), 88–96.

Sari, P., & Nugroho, A. (2021). Pengaruh perubahan desain terhadap biaya dan waktu pada proyek pembangunan gedung perkantoran. Jurnal Teknik Sipil dan Arsitektur, 10(1), 55–64.

Smith, N. J. (2014). Managing risk in projects. London: Routledge.

Susanti, R., & Prasetyo, A. (2018). Analisis keterlambatan proyek konstruksi ditinjau dari faktor manajemen waktu. Jurnal Teknik Sipil dan Perencanaan, 20(2), 75–84.

Turner, J. R. (1999). The handbook of project-based management. New York, NY: McGraw-Hill.

Yuliana, D. (2021). Evaluasi manajemen biaya pada proyek konstruksi gedung bertingkat. Jurnal Rekayasa Konstruksi, 7(1), 25–33.

Yunus, A. I., Ulfiyati, Y., Mulyati, E., Priana, E. S., Roring, H. S. D., Junaed, I. W. R., Yuliana, A., Zayu, W. P., Ghozali, Z., Stighfarrinata Rizky, Safitri, F. A., Sandi, E. A., Wantouw, F., & Syarif, H. U. (2024). Manajemen Proyek (M. G. Indrawan,

Wideman, M. (2002). Project and program risk management: A guide to managing project risks and opportunities. Newtown Square, PA: Project Management Institute.

Wijaya, H. (2019). Manajemen risiko pada proyek konstruksi gedung bertingkat. Jurnal Teknik Sipil dan Lingkungan, 7(2), 101–110.

Downloads

Published

2025-07-29

How to Cite

Muhammad Malik Abdul Jabbar, & Era Agita Kabdiyono. (2025). Analysis of Design Change Management in a Construction Project at Jl. Duta Permai 2 No. 6, Pondok Indah: Case of Owner Mr. Patrick. International Journal Science and Technology, 4(2), 214–222. https://doi.org/10.56127/ijst.v4i2.2289