COST ANALYSIS WITH CRASH PROGRAM OF KEROBOKAN PARKING LOT BUILDING BALI
DOI:
https://doi.org/10.56127/ijst.v3i2.1571Keywords:
Critical Path Method, Crashing Program, Overtime Work, Time AccelerationAbstract
Kerobokan Bali Parking Building is one of the buildings that uses steel material as the main structure. The building which has a height of 13.97 meters, a width of 32.8 meters, and a length of 16.18 meters has a construction plan duration of 248 calendar days starting from July 2023. Known critical trajectory activities will be carried out a crashing program analysis with the aim of accelerating time by using one method, namely overtime work with a duration of 4 hours. Based on the analysis that has been carried out with the help of the Microsoft Project 2019 application, there are 16 lists of activities included in the critical trajectory. In writing this thesis, it will be mentioned in the form of a line code in Microsoft Project 2019, namely 569-573-579-580-581-606-585-586-590-591-595-596-600-601-602-612. In addition to knowing the list of critical path activities, this thesis also accelerates the duration with an additional 4 hours of overtime and calculates the total cost of the acceleration. After acceleration, it is known that the duration decrease is 61 days with a normal duration of 248 days to 187 days and shows a time efficiency of 0.245%. The total initial cost with normal duration is Rp 8,822,280,000.00 while if the project is accelerated, the project cost becomes Rp 8,901,216,104.5 by showing an additional cost of Rp 78,936,104.47.
References
Akhir, T. (2019). Analisis Crash Program Menggunakan Microsoft.
khoerul ummah. (2022). No Titleהכי קשה לראות את מה שבאמת לנגד העינים. הארץ, 8.5.2017, 2003–2005.
Nur Yaqin, H., Teki Tjendani, H., & Witjaksana, B. (2023). Analysis of The Acceleration of Time and Cost of Implementing Building Construction Projects Using The Critical Path Method (CPM) Method. Devotion Journal of Community Service, 4(2), 336–346. https://doi.org/10.36418/dev.v4i2.388
Republik Indonesia, P. (2021). Peraturan Pemerintah Nomor 35 Tahun 2021 Tentang Perjanjian Kerja Waktu Tertentu, Alih Daya, Waktu Kerja dan Waktu Istirahat, dan Pemutusan Hubungan Kerja [Government Regulation Number 35 of 2021 concerning Work Agreements for Certain Time, Outsourcing, W. Peraturan Pemerintah Republik Indonesia Nomor 35 Tahun 2021, 086142, 42. https://peraturan.bpk.go.id/Home/Details/161904/pp-no-35-tahun-2021
Syaputra, I. (2019). Analisa Penjadwalan Pelaksanaan Pekerjaan Proyek Dengan Metode CPM Dan PDM Pada Peningkatan Jalan Sei Pakning (Km 130) – Teluk Masjid – Simpang Pusako Kabupaten Siak. Km 130.
Husna, R. A., Ilmiyah, N. F., & Resti, N. C. (2022). Implementasi CPM dan PERT dalam Memprediksi Durasi serta Biaya Pembangunan Musala Al-Ikhlas di Kotawaringin Barat. Journal Focus Action of Research Mathematic (Factor M), 5(1), 97–109. https://doi.org/10.30762/f_m.v5i1.633